An airport has 4 gates. If the weighted average gate occupancy time is 30 minutes and gate utilisation factor is 0.5, then the capacity of the gate will be___________________?
A. 1 aircraft per hour
B. 2 aircrafts per hour
C. 4 aircrafts per hourCorrect Answer
D. 16 aircrafts per hour
Correct Option: C. 4 aircrafts per hour