Drop manholes at the junctions of sewer lines, are provided if________________?
A. Invert level of a branch sewer is more than 60 cm that of the main sewerCorrect Answer
B. Sewer line runs along a main road
C. Ordinary manhole cannot be built
D. Two sewer lines intersect
Correct Option: A. Invert level of a branch sewer is more than 60 cm that of the main sewer