Relevant Competitive Tests:
Earliest finish of an activity is always_______________?
A. greater than earliest event time of the following node
B. less than earliest event time of the following node
C. less than or equal to earliest event time of the following nodeCorrect Answer
D. greater than or equal to earliest event time of the following node
Correct Option: C. less than or equal to earliest event time of the following node
This question has been verified by the PakPrep community moderation network for competitive examination accuracy.
Subject Overview
Explore thousands of solved past paper MCQs for Civil Engineering Mcqs categorized with explanations.
Browse All Civil Engineering Mcqs MCQs →