For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is__________________?
A. 8 days
B. 9 daysCorrect Answer
C. 10 days
D. 15 days
Correct Option: B. 9 days