In PERT analysis, the time estimates of activities and probability of their occurrence follow_______________?

A. normal distribution curve
B. Poisson’s distribution curve
C. Beta – distribution curveCorrect Answer
D. none of the above
Correct Option: C. Beta – distribution curve