In resources levelling________________?

A. total duration of project is reduced
B. total duration of project is increased
C. uniform demand of resources is achievedCorrect Answer
D. cost of project is controlled
Correct Option: C. uniform demand of resources is achieved

This question has been verified by the PakPrep community moderation network for competitive examination accuracy.