Pick up the correct statement from the following?
A. The maximum rate of storm runoff is called peak drainage discharge
B. Rational method of estimating peak run off, may be used precisely for areas less than 50 hectares
C. The period after which the entire area starts contributing to the runoff, is called the time of concentration
D. All the aboveCorrect Answer
Correct Option: D. All the above