Pick up the incorrect statement from the following?
A. Lead is the average horizontal straight distance between the borrow pit and the place of spreading soil
B. The lead is calculated for each block of the excavated area
C. The unit of lead is 50 m for a distance upto 500 m
D. The unit of lead is 1 km where the lead exceeds 2 kmCorrect Answer
Correct Option: D. The unit of lead is 1 km where the lead exceeds 2 km
This question has been verified by the PakPrep community moderation network for competitive examination accuracy.