The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is ________________?

A. 1.00 m3
B. 1.25 m3Correct Answer
C. 1.50 m3
D. 1.75 m3
Correct Option: B. 1.25 m3

This question has been verified by the PakPrep community moderation network for competitive examination accuracy.