Which of the following term is best defined by the statement:”the degree of uncertainty that the product will meet its requirements and be fit for its intended use.”?

A. Performance riskCorrect Answer
B. Cost risk
C. Support risk
D. Schedule risk
Correct Option: A. Performance risk