Which two models doesn’t allow defining requirements early in the cycle?

A. Waterfall & RAD
B. Prototyping & SpiralCorrect Answer
C. Prototyping & RAD
D. Waterfall & Spiral
Correct Option: B. Prototyping & Spiral